Lakefront Home

The owners of this property chose to demolish this 1969 3 room camp, making way for a new traditional New England style 4 bedroom lakefront home, with both an attached and a detached garage, along with a new perched beach


  • Demolition of the old home begins

  • The lot is cleared for new construction

  • Site crew moves in for stump removal and site clean up

  • Driveway is stabilized for heavy equipment traffic

  • Gilford Well moves in to drill the well

  • Perched beach construction has begun

  • Retaining walls progress and granite steps installed

  • Perched beach is complete

  • Footings for detached garage are set and poured

  • New docks are installed

  • Continued progress on the detached garage foundation

  • The house location is staked

  • Detached garage foundation is backfilled

  • Detached garage utility conduits are all in place. Inspection complete, backfill complete.

  • Footings for the house are set and poured

  • The slab at the detached garage is poured

  • House foundation rebar and form panels were installed, and foundation walls are being poured

  • House foundation is waterproofed and insulated, drainage and backfill in progress

  • The under slab vapor barrier and insulation are installed, ready for the slab

  • Basement slab has been poured and is complete

  • Detached garage walls are being framed and sheathed

  • House floor joists are set

  • Trusses for the detached garage are delivered to the site

  • Installation of trusses has begun

  • Detached garage roof trusses are set, bracing and blocking are being installed to get ready for sheathing

  • Roof sheathing installation has begun

  • Utility line trenching is complete

  • The detached garage is all sheathed and gable overhangs are framed and installed

  • The house is ready for the main floor sheathing

  • House main floor sheathing complete, walls being framed

  • Detached garage roof trim complete, soffit installation begins

  • Detached garage soffits installed, garage door openings framed, windows installed

  • Underground propane tank is set

  • Detached garage siding is progressing, gable brackets are installed

  • Upper level floor sheathing is being installed on the house

  • Continued progress on the detached garage siding. Roof shingles have been installed

  • House upper level exterior walls are underway, the north gable has been raised

  • Upper level walls and rafters are coming along nicely

  • Heavy timber trusses being fabricated on site for sections of the main house

  • Roof sheathing and ice and water shield are installed on part of the attached garage

  • SIP's panels are delivered to the site

  • Ice & water shield is installed on parts of the house

  • Trusses are being set

  • Roof and exterior walls framed, sheathing being installed

  • Continued progress on truss installation and roof sheathing

  • Framing interior partitions

  • Garage doors are installed in the detached garage

  • Trusses and timber rafters set

  • Progress on the roof sheathing and ice & water shield

  • Interior framing progress

  • Ice & water shield installation is complete, the mason has set up tenting

  • The masons make progress on the entry piers

  • The masons have completed the entry piers

  • Roof trim installation nearing completion

  • Upper level onterior partitions are complete

Go Back